Project Location: | Mudi V.D.C., Myagdi District |
Latitude: | 28°33’01”N to 28°34’18” N |
Longitude: | 83°21’50”E to 83°23’49”E |
Name of the River: | Myagdi Khola |
Type of power Generation: | Run-of-the-river |
Gross Head: | 95m |
Design Discharge: | 12.5cumecs |
Water way Length: | 1900m |
Installed Capacity: | 12.5 MW |
Average Annual Energy: | 58.28 GWh |
Transmission Line: | 30 Km |
Access Road: | 25 Km |
Total Average Annual Generation: | 58.28 GWh |
Dry Energy (Poush to Chaitra): | 18.52 GWh |
Wet Energy (Baisakh to Mangsir): | 39.76 GWh |